T O P
I_ThinkYouAreGreat

A scale, I’d put it next to the north arrow


saidnamyzO

Do you need to add storm utilities still? Also, waterlines usually have separation requirements to sanitary sewer (sometimes storm too). Where I live, horizontal separation between water and sewer is 10’ from outer edges of the pipes, and water has to be 12” (maybe 18”?) higher at any crossings (can be closer if sleeves and/or CDF is used as extra protection from contamination). I think you can get away with it on a private single-family residence, but it’s still good practice to separate them; check to see if there are requirements from the local health district and municipality.


lmrgawdly

Thanks, this is a very old and rural plot, so standards were very relaxed and most of the existing structures and utilities were put in place before you had a 'building control' or needed planning approval to start developing. The idea was to accurately map existing features, prepare a reference dxl/csv for potential future activities on the plot (demolition, extensions or new developments)


Marmmoth

Sewer - Sewer lines shouldn’t have hard turns like that. It’s asking for a clogging problem. It’s fine for water and power but not sewer. Yes you’re showing small sweeps but it’s still problematic. Basically you should avoid 90 degree turns in sewer at all costs even with sweeps. Smaller turns (elbows) such as 45 degrees are fine, but usually there’s a clean out at this location. If a 90 degree turn is required usually we’d add a manhole, but as this is private property I’d use (2) 45 elbows spaced apart with at least one clean out. - Delete the jug to hug the northwest of the 213sqm house and I would run two 45s and add a clean out at the corner. (If you’re not showing clean outs at this level of design that’s fine) - Delete the jog on the north side of the 213sqm house west of the septic and route it diagonal from manhole to the septic. - Also, why is one septic tank feeding into another septic tank? - You’re showing septic tanks, but the end of the line is not showing a drainfield. Where are your septic tanks draining to? Power - Parallel buried power conduits are typically installed in the same trench with very little separation. - Show the power lines from 49 and 63 houses to be parallel with uniform offset until it gets to 213 house. Water - I’m not sure about the codes in your area, but there may be a requirement to separate water and sewer. Where I live code it says you need to have a 10 foot horizontal separation. Some of your lines look pretty close together. Don’t worry about perpendicular crossings though at this design level.


liquidporkchops

I’d show easements, they’re calso move my onsite infrastructure away from from where PUE’s probably exist. I’d also show the driveway, leech field, phone, CATV and building uses. Shading back the stuff to be decommissioned would be a good idea too. I’d show the leech field and fate for the septic to be decommissioned as well.


lmrgawdly

Shade the decommissioned stuff and differentiate them from the ones in use? Thanks


mz_engineer12

Pipe info - diameter and material. Also good to show the valves on the water line and clean outs on the sewer.


MeatManMarvin

Elevations and depths would be great.


lmrgawdly

Depths right under the lines; DOC (Depth of Cover)


PlantDaddys

Any abbreviations should be listed in your legend


ProfessorGarbanzo

Web Mercator projection is just about everywhere because it’s great for web mapping but is a big no at the site scale . Those words are a big red flag for something showing dimensions. Recommend change to a regional projected coordinate system and doublecheck your areas / distances. Even UTM would be a big improvement, for site work I’d use something more local but it might take you some work to track that down if you’re not familiar. In the US I’m talking about state plane or county systems but I assume you are somewhere else (meters) https://gisgeography.com/web-mercator-projection/


ProfessorGarbanzo

Obviously I’m a GIS nerd, I’ll add that the only reason I noticed is because you bothered to list the projection which is important but often skipped. So good work on that. That being said I almost never see all the details of the projection (like false easting) listed on a figure, you can just provide the name and for bonus points the projection id (epsg, or esri #). This issue with web Mercator comes up frequently because often the first thing people add to a figure is a streaming basemap and the project adopts that coordinate system. It really does cause errors in measurements though.


hotpotatoinmyrisotto

This is in your undergrad? This is awesome! I never did cool/ useful stuff like this. Sounds like you got a good school/ professor


ODST_Spartan_91

Valves? I often find myself looking at potable water utility surveys to locate cutoff/isolation valves.


kiskaadee_help

Maybe add lot pins. Scale in=ft. Show north arrows on little maps on the right. Parcels lots. Usually you don’t do colors on the platsheets, line weights, types and transparency is what you use. Add a sheet number on the bottom [Sheet 1 of 3]. Show areas in AC. Bldg areas in sq ft.


lmrgawdly

Thank you very much, I'll add those and use b&w for every feature 👍🏽


liquidporkchops

Dude. The plans are in the metric system.


ruffroad715

In this case cm=m


CE_2020

Here's some recommendations: Sheet 1 - existing conditions Sheet 2 - proposed conditions I always like having structure and pipe tables (for larger projects). I'm assuming you're not using CAD or Civil 3D.


zdza

Sheet 1: locality plan with block highlighted, legend, and drawing list Sheet 2: existing services drawing Sheet 3: proposed services drawing Exisiting services example; water eW (add diameters on each run), proposed water W (in a thicker pen)


Spiritual_Ferret_192

The stated scale only works for a specific page size. I would add a reference to whatever page size it's expected to be printed at (e.g. 1 cm = 1 meter @ A3). Unless I've missed that somewhere, apologies if so. Alternatively, you could use a scale bar. Also, not sure if it's really needed for standalone drainage systems, but they typically have inverts (elevations) recorded at the beginning/end of pipe segments (manholes typically).


Unfair-Thought5814

Telecom.


lmrgawdly

No telecom lines, just one antenna mounted on the roof (internet) but all the cables run inside so I wasn't sure how I would represent that


Unfair-Thought5814

It's prudent to include a duct for telecom even if satellite internet is planned for Day 1.


lmrgawdly

Got it, these are existing services so they didn't make provisions for telecomms but I think I'll regularize the plot to follow current standards as an exercise, i.e space utilities, add manholes to the drawing as advised in this thread, thanks


Unfair-Thought5814

That sounds great. Now that I see where this plot is located I understand why it's satellite only.


EatPrayFart

It seems like everyone has given you good advice. I'll add from a plan presentation perspective, be consistent with your labeling. He an example of grading and utility plan from a project from a few years ago. [Example Plan](https://imgur.com/a/jtsWEWo)


lmrgawdly

even better having a visual example of how a utility plan would look like, thank you very much.


rmarshall391

Pipes and cables usually have manholes or draw pits at every change in direction. So your drawing seems to lack manholes and drawpits. These are usually numbered aswell like MH01, MH02 and have cover level and invert level. And usually have a separate supporting document called manhole cards with more detailed info


lmrgawdly

There were manholes on site, I just skipped over them, but I will go back and get those surveyed in


ruffroad715

Maybe a hydrant or at least a Tee at the end of the water line. Gate valve at the Point of connection to city main. Probably a meter too


ruffroad715

Check your contour lines too. 6m jump from 183 to 189


Foldingtrees

Change the arrow thickness, it's the same as the contours


RenownedDumbass

Huh, metric uses "sqm" just like we use "sq ft" in the US. I don't know why both of those don't just use a superscript 2, looks better imo. But I never see superscripts on plans.


DahGreatPughie

We use m² and m³ in the UK unless I'm having a really bad day and can't find the ² symbol in autocad idk what the standard is elsewhere I swear I saw some German drawings with m² on them too tho


jeaby

"PRINT IN COLOUR"


maspiers

Should the power & water go off site somewhere?


half-a-cat

Less bends in sewer line. Add dimensions or notes with the minimum separation distance between water and sewer lines, a scale near the north arrow. Looks great!


CivilMaze19

Unless the formatting you’re using is a requirement I think you could abbreviate alittle more and also almost all design drawings I’ve worked with (in the US) has all capitalized text. Examples: 120V OVERHEAD PWRLINE - 120V OHE B. PWRCABLE - UGE B. WTRLINE - (size) WL B. SEWAGE - (size) WW or SS


18_USC_1001

Drain field?


Hot-Performance-7551

Legend with the utility owners


lmrgawdly

YES! I will do just that, thanks


DahGreatPughie

Those seem like long runs without inspection chambers, check what your local standards are for that invert levels are useful at chambers too. A page size next to your scale is needed too do they typically show scales like that in your country? In the UK we would just show that as 1:100 @ a3. It seems a pretty decent drawing though especially for an undergrad nice one.


ilikeweed--alot

I would add flow arrows, maybe locate the public water main (assuming that’s the water source), capitalize all text, use line types with W, S, and E within them to show as water sewer, electric, etc. Those are more formatting as opposed to design but just some extra things to help drawings look clean


lmrgawdly

I thought about adding flow arrows but I felt the drawing was too cluttered


kendricklemon

Maybe slopes too? I work in land development and we usually have pipe material, depths, slopes, diameters, lengths, and any clean outs/man holes/ connections on our plans


rasin_staynMx

Not mandatory but something to keep in mind: We rarely print in color, even if you do it’s important to print it in grey scale to see if the colored lines remain distinguishable when gray. We distinguish lines types with weight, dashes, symboled dashes, and gray scale. I think it’s almost inevitable for a drawing to become gray scale or black at some point in its life cycle.


lmrgawdly

Got it! I'll play around with the line properties and export it in grey scale


[deleted]

Add nearby water main valves, manholes which should be adjacent to the buildings and add the lateral ties from buildings. As much as details are the best for construction engineers and inspectors bcuz its makes our lives much easier.


impaler92610

Proposed pipe elevations, i.e. invert elevations with respect to finished grades or surfaces. Might want to add a profile for each pipe; conflicts; points-of-connection; and details...trench detail, depth of over-excavation, pipe bedding depths and materials.


Darksouls1020

Add the schedule of the total area plot. Adds more detail for the entire thing.


ItsAChainReactionWOO

An E in sptic tank


alphabet_order_bot

Would you look at that, all of the words in your comment are in alphabetical order. I have checked 1,334,642,096 comments, and only 257,049 of them were in alphabetical order.


ItsAChainReactionWOO

Bot good


somethingdarksideguy

For the love of christ fix your leaders.


Bonty-67

Leaders are atrocious, try mleaders. Another thing that seems to be missed is that there isnt really a titleblock - drg number, date, scale, drawn by, etc. Basic stuff but required for all documents


kaclk

You’re missing natural gas.


lmrgawdly

Most heating/cooking is done using electricity/portable gas cylinders in this part of the world so you won't find those anywhere


marckley88

What's the source of the water. And I'm sure you probably need a drain field to dispose of the sewage. Size, length of pipes. And slope on the pipes.


myoneseriousaccount

Maybe a couple tiny north arrows in the locus maps on the right. They don't seem to be the same orientation as the map. General notes describing data collection methods, qualifying statements, call before you dig(don't know if you have that where you're at). ASCE has SUE levels that describe what lengths you went to to gather this data.


reh102

Legend? Utility sizes/material


lmrgawdly

Will add a legend later, wasn't sure what to put there. I don't have info on pipe widths or material (I could take a guess but I don't want to be wrong)


reh102

Assume based on local code /water/server demands per day per person. List the source. Way better than nothing


reh102

And where is the water hooked up to?


PhlegmOn237

Deez


lmrgawdly

![gif](giphy|3oKHWw4HiAsueq9SBq)


IEngineerJR

My first thought is are you a land surveyor? Did you survey those dimensions showing the boundary? We’re I live, it’s illegal for anyone but a surveyor to make claims on where property boundaries are. By putting those dimensions you expose your self to liability when they are proven to be inaccurate. Just my opinion.


lmrgawdly

I shot the boundaries and swept the features on site as an exercise so this is not an official document for submission and won't influence any activities on site (but could act as a visual reference), the owners still have to get a proper survey done.


IEngineerJR

There’s literally a law suit in court here in the states, California on this exact issue. Where a tech startup is dropping property boundaries on an aerial topo map. From Google imagery.


IEngineerJR

“Act as a visual reference “ equals evidence in a law suit. Do your self a favor and at least put a statement that these boundaries are not defined by a land surveying professional and a survey is needed for the precise location of property corners and therefore measured distances.


lmrgawdly

Understood, I'll add a statement


stonededger

Rainwater drainage line and fire water line? Maybe no need for fire water if this is private housing.


phillycheese1337

Need to add the pipe sizes and either set out points or offset from features.